Saluran di Jalan Flamboyan Mulai Dipasang U-dith

Channel Repair on Jl. Flamboyan Kebon Jeruk Has Reached 80 Percent

West Jakarta Water Resources (SDA) Sub-agency is currently repaired water channel on Jl. Flamboyan, Kebon Jeruk, by installing it with U-ditch and covers.

Our target is to complete it by the end of June

West Jakarta SDA Sub-agency Drainage Maintenance Section Head, Wawan Kurniawan mentioned, U-ditch and covers installation work has been carried out since June 12, 2021.  

"U-ditch and channel covers will be installed on channel along 80 meters with width 60 centimeters," he informed, Thursday (6/24).

Channel on Jalan Merpati in Meruya Utara Widened

His side deployed 1 unit mini excavator and 13 personnel equipped with hoes, crowbars, sledgehammers, hammers, and buckets.

"Current progress has reached 80 percent. Our target is to complete it by the end of June," he said.

He hopes this repair can optimize water channel capacity thus it can minimize inundation, especially during heavy rains.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1589 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1440 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1303 personFolmer
  4. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye967 personDessy Suciati
  5. MRT Phase 2A Northbound Tunnel Excavation Completed

    access_time09-07-2026 remove_red_eye844 personAldi Geri Lumban Tobing